Transit Priority & Mobility Enhancements This is a demonstration project to install intelligent transportation system (ITS) components within the Watt Avenue corridor to improve traffic management and safety. The project will be tied into County Traffic Operations Center. Transportation system benefits will include:
Planned ITS improvements include:
Tentative Schedule Preliminary Study, 2006 to 2007Design, 2007 to 2008 Environmental Study, 2007 to 2008 Right of Way Acquisition, 2007 to 2008 Construction, 2007 to 2008 Funding The total estimated project cost is $2.5 million and will be provided by Measure A Sales Tax funds (50%) and TEA-21 funds (50%). Contact Information
Doug Maas, Project Manager |
||
|
|
|||
|
|||