Madison Avenue - Sunrise Boulevard to Hazel Avenue

Project Description

The Madison Avenue (Sunrise Boulevard to Hazel Avenue) improvement project that will provide a number of roadway system benefits including: 

  • Improved roadway safety.
  • Increased traffic capacity to ease congestion and delays.
  • Improved bicycle and pedestrian facilities.
  • Meet Americans with Disability Act requirements.
  • Beautification of the project area.

Planned roadway improvements would include:

  • Widening Madison Avenue from 4 to 6 lanes between Sunrise Boulevard and Hazel Avenue in the City of Citrus Heights and the Orangevale area. Project implementation requires a cooperative agreement with the City of Citrus Heights.
  • Construction of a 12-foot wide raised, landscaped median along Madison Avenue.
  • Modifying existing traffic signals, sidewalks, curbs and gutters.
  • Roadway improvements for ADA compliance, transit access and bicycle and pedestrian facilities.

Tentative Schedule

Preliminary Study, 2004 to 2009
Design, 2008 to 2011
Right-of-Way Acquisition, 2010 to 2012
Construction, 2012

Funding

Estimated total project costs are $25 million and will be provided by Developer Fees and Measure A Sales Tax.

Contact Information

Jerry Cern, Project Engineer
Associate Civil Engineer
916-875-4769
cernj@saccounty.net



Back to Top of Page
© 2009 County of Sacramento.
Privacy Policy Conditions of Use Accessibility Policy Alternative Formats