Project Description

This project will construct sidewalks to fill in gaps at 14 locations in accordance with the Sidewalk Construction Project Priority List. These include locations where pedestrian volumes and adjacent vehicle volumes are relatively high, and where it is unlikely that property development or redevelopment will occur in the near future. Benefits of this sidewalk continuity project include:

  • Improving pedestrian safety.
  • Providing continuous sidewalk facilities.
  • Improve appearance and uniformity of the street infrastructure.
  • Improve accessibility for disabled pedestrians.

The locations are:

Phase Location Phase Location
3 Alta Arden Expwy (west of Morse) 2B Annadale Lane (east/west of Edison to Auburn)
2B Auburn Boulevard (west of Annadale) 3 East Parkway (south of Florin Road)
2B Edison Avenue (East of Watt) 2B Edison Avenue (west of Watt)
2B El Camino (Loretto High School to Burgundy ) 2B Fulton Avenue (Carson Way intersection)
3 Fair Oaks Boulevard (east of Miles)   Kiefer Boulevard (Huntsman to North Kiefer) [transferred to the North Kiefer Boulevard (Closure of Kiefer Boulevard) Project
3 Gerber Road (Power Inn Road intersection) 3 Sierra Boulevard (Fulton to Howe)
2B Northrop Avenue (Howe to Bell) 2B Watt Avenue (Greenview to Robertson)
2B Watt Avenue (West Way to north of Sierra View)    

Tentative Schedule

Preliminary Study, 2003 to 2006
Design, Phase 2B: 2003 to 2007, Phase 3: 2003 to 2008
Environmental Review, Phase 2B: 2003 to 2006, Phase 3: 2003 to 2008
Right of Way, Phase 2B: 2007 to 2008, Phase 3: 2008 to 2009
Construction, Phase 2B: 2008 to 2009, Phase 3: 2009

Funding

The estimated total project cost for phase 2B is $1.7 million and the estimated total project cost for phase 3 is $1.3 million. These projects will be funded by the Measure A Sales Tax and the Sacramento Housing Redevelopment Agency's Federal Community Development Block Grant. 

Contact Information

Anthony Voo, Project Engineer
Associate Civil Engineer
916-874-7871
vooa@saccounty.net