Project Links: Project Home |
Countywide Sidewalk Continuity Project Project Description This project will construct sidewalks to fill in gaps at 14 locations in accordance with the Sidewalk Construction Project Priority List. These include locations where pedestrian volumes and adjacent vehicle volumes are relatively high, and where it is unlikely that property development or redevelopment will occur in the near future. Benefits of this sidewalk continuity project include:
The locations are:
Tentative Schedule Preliminary Study, 2003 to 2006 Funding The estimated construction cost for Phase 2B is $1.7 million, Phase 3A is $415,000, and Phase 3 is $1.6 million. These projects will be funded by the Measure A Sales Tax and the Sacramento Housing Redevelopment Agency's Federal Community Development Block Grant will provide funding for Phase 2B. Contact Information Anthony Voo, Project Engineer |
||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||